Midway Rising Starts at Dixieline, So Pechanga Arena Keeps Its Winter Dates

At the east end of the city-owned land on Sports Arena Boulevard, past the big parking lot and the round roof of Pechanga Arena, sits Dixieline Lumber. The approval that got the most coverage this month puts its first building on that parcel. Voice of San Diego reported the day after the City Council vote that Midway Rising's new 16,000-seat arena "will be where Dixieline Lumber sits now," and that the developers expect it to be close enough to the Old Town Transit Center to walk to.

That location answers most of what a nearby resident wants to know this winter. The plan puts the new arena next to the old one. The existing arena, its lot and the events that fill both stay where they are while the replacement is built at the east end of the same property.

The yes came on November 9

On Nov. 9, 2026, the San Diego City Council unanimously approved the Midway Rising redevelopment of the 48.5-acre Sports Arena site. The City's project page lists the plan as 2,000 affordable homes, about 2,250 market-rate homes, the 16,000-seat entertainment center, shops and restaurants, and 14.5 acres of parks and public spaces. Voice of San Diego put the project at $4.2 billion as of the November vote.

According to the City, Pechanga Arena will stay open until the new entertainment center is fully built and ready to open.

Phase one happens beside the old arena

Times of San Diego laid out the sequence before the first committee vote in October. Kroenke's Midway Rising team begins with a first phase that includes the new arena on the eastern side of the lot, surrounding mixed-use buildings and a public outdoor space, while the existing sports arena stays in operation. The new arena is estimated to take about five years to build. KPBS reported on Nov. 10 that the old arena can be demolished and its area redeveloped only after the new venue opens.

The lease paperwork follows the same order. In September the City Council extended the current arena operator's interim lease, and the new end date is Dec. 4, 2031. The City staff report also counts parking-lot rentals and swap-meet use among the arena's existing revenue sources. Those sources stay in the rent structure while the site is prepared and the new entertainment center is built. The report describes the work ahead as site infrastructure, transportation, and parks and public spaces, prepared without interrupting the existing arena.

The arena that gets torn down is the last piece of the site to change, so the near-term calendar looks like any other winter at the arena.

This winter at the old arena

The first home weekend after this post publishes is a hockey weekend. The San Diego Gulls' 2026-27 schedule has them hosting Iowa on Friday and Saturday, Nov. 20 and 21, and Springfield on Jan. 8 and 9. The Pechanga Arena events page lists programming into January.

Kobey's Swap Meet still calls itself "San Diego's Largest Outdoor Marketplace," open Friday, Saturday and Sunday, and its site lists a Saturday, Dec. 12 event. Its homepage describes it as a swap meet that has been running for 44 years. The arena lot has been a weekend errand for a long time, and the approved deal still counts swap-meet use as part of how the arena earns its rent during construction.

If your winter weekends already include a Gulls game, a concert, or a morning walking the Kobey's rows before lunch at Liberty Station, the Nov. 9 vote leaves those plans alone. Our recent look at the restaurant openings around Liberty Station and Shelter Island covers the nearby food stops for a Saturday in this corner of town.

The Dixieline end of the property

The Dixieline parcel is where a resident will first see the project, and no work has a start date there yet. KPBS reported in August that the developer hoped to break ground by the end of 2027 if the Council approved the project. The City expects to finish setting up an infrastructure financing district with the County in about a year.

Dixieline's tenancy on the site goes back a long way. The agreement's title records include a memorandum of the City's lease to Dixieline Lumber Company dated 1994. Voice of San Diego noted that the City stopped signing new long-term leases with businesses around the Sports Arena more than eight years ago, when it first started planning a large redevelopment of the land.

How the site reached this point

That planning started under former Mayor Kevin Faulconer. In 2022 the City Council picked Midway Rising from three shortlisted teams. Courts later threw out two voter-approved height-limit measures for the area, and KPBS reported that two state bills on the project, SB 344 and SB 958, were signed Sept. 29, 2026. Voice of San Diego described the years before the vote as "one failure after another."

The final version changed in October. Councilmember Kent Lee brought an amendment requiring the 2,000 affordable homes to be newly built on the site, not transferred in from other projects. After the vote, Voice of San Diego quoted him: "It preserves the city's ownership of the land. It now includes stronger protections to deliver new affordable housing and to ensure that the city benefits in the act of a refinance."

What the finished site adds around it

Most of what neighbors will eventually use sits outside the arena itself. The Independent Budget Analyst estimates the developer will spend about $460 million up front on infrastructure around the site, including road work, sidewalks, lighting, parks and bike lanes, with about $378 million of that potentially recovered through the financing district the Council voted to pursue. That spending is meant to support the walk between the new arena and the Old Town Transit Center. Voice of San Diego reported that the developers believe their investment will lead to more investment along that route.

The deal keeps the land in City hands. Times of San Diego reported that the City receives $100,000 a year in rent for the first 15-year period. The IBA estimates the City could collect about $884 million to $1.23 billion in ticket fees and rent over the century-long life of the agreements.

The 14.5 acres of parks and public space, the shops and restaurants, and the homes come in phases spread over several years. The first one a resident will see is the new arena at the Dixieline end. Until that building opens, Pechanga Arena, its parking lot and its weekend crowds stay where they are.

If you have PCS orders to San Diego and want to know how a multi-year build at the Sports Arena site fits with the streets you're looking at, Alanna Strei Realty Group can walk you through what's scheduled there and what isn't. Book your free VA relocation consultation.